floors 12 to 20 hours depening on how much floor
rockers Outers, 16 hour for the pair
mini tubs On a convertible 40 hours
quarters 15 hours each including outer wheels houses
rear tail panel 8 hours
trunk lid included

That is about 100 hours for sheetmetal. I know they did some custom treatment to your quarters.

If the sheetmetal is right, your 200 to 240 hours from painted.

What is his hourly rate?