We are quite a bit behind the original release date of March 2012, and the later updated date of mid-summer 2012. But, we are chugging along and hope to be done in the next few months. That will give us seat time before next year's events, which we will need.

Bulldawg was shooting for having the engine and trans painted, and reinstalled in time for our upcoming Meet & Greet at their shop, this coming Saturday. Haven't heard from them in a few days, but hopefully they were able to get that tackled, and we'll get new pics this weekend.

Dark Dog Customs is handing the shell back to the body shop, as they have all the measurements and mock up pieces they need to start the interior. Hopefully the shell will leave their shop tomorrow or Saturday morning.

Body work: they are estimating about 2 weeks worth of work on finish body work. But based on his current schedule, that may take 4-8 weeks to get done. Once it is finished, it will be ready for paint, and then back to reassembly.

LED update: Spaghetti Engineering has finished the prototypes, and we are getting the first production unit! It should be here next week sometime, and we are very excited. Here are picture of the kit that they emailed to me: