Yes, we used 2 12" long pieces of bar per side (8/footing). We didn't go all the way across so I didn't have to worry about hitting bar when drilling holes. We also undercut (keyed in) the footing hole to the existing slab per most lift manufacturers' instructions. Can't wait to get the lift in!