Originally Posted by Cosmo mentis View Post
What's the guesstimate to when JA 2.0 will be completed?

A lot depends on a couple key partners. Sled Alley is set to rework the following:

Mount the new C&R cooling stack
New trans crossmember
New BIG induction tube
Move dry sump tank
Fix the fire wall and random holes in bottom of car
Repaint bottom, firewall and engine bay

Thomson Auto has the engine parts on order. I hope to have the new engine running in 4 weeks

Ryan Kuhlenbeck if flying in this week to help me wire the car. We are coping the electrical architecture of Hellfire. It is also fun to hang out with him.

When the car gets back from Sled Alley I need to:

Finish the wiring
Make ABS brake lines
Fuel lines
Trans and diff cooler lines
Re Assemble
New carpet
New dash with data logger

So if all goes to plan JA 2.0 should be running mid April.

The key to getting it done is not too much scope creep.

Stielow