View Single Post
  #5  
Old 05-24-2007, 05:37 AM
HRBS's Avatar
HRBS HRBS is offline
Senior Member
 
Join Date: Oct 2006
Location: New Jersey
Posts: 1,190
Thanks: 0
Thanked 1 Time in 1 Post
Default

My problem is two fold.
Not only are the aftermarket parts getting pricey AND fit like crap, but the supply is running short because of high demands for these parts.
I had needed two quarters for the Stang project and everyone only had the passenger sides available. I was told 2-4 week lead time for the driver side.
Not as easily said. I was attempting a fastback conversion on this conv. and needed BOTH before I started because of the difficulty in matching the deck lid to the quarters. Long story short, 2-4 weeks turned into 6 and I couldn’t touch the car until all the parts were here. I lost out on 6 weeks of precious build time. Those 6 weeks will make or break me in the up coming weeks!
__________________
HRBS on Facebook
Reply With Quote