They got back on things here this week. I believe we got about 5" of rain, so the excavator had to pull off for a week. Looks like site prep will be done this week and should be ready for concrete towards the end of next week.
The whole time they were excavating at our house —- I kept thinking how much I was on the hook for and I hadn’t even pounded a 2 X 4 together yet...... LOL
The Following User Says Thank You to GregWeld For This Useful Post:
Thanks for the kind words. Unfortunately, the concrete contractor kinda screwed me. He took another job and then the winter set in here in northern WI.
The site is all prepped and ready to go. It will work out for the best letting the site go through a frost cycle besides all of the rain and snow load to help settle. Patiently waiting.......................
The Following User Says Thank You to NAPA 68 For This Useful Post: