A true effective slope to the drain could be a wonderful thing if indeed you do plan to do a lot of car washing, wet sanding, whatever. But like others have said, if it is not what you wanted and you plan to be in the shop a lot...

Every fire station I've ever worked at has pitched floors and at least four large drains... the low spot in the floor is never at the drain. It's always a foot away and you end up pushing water up into the drain. When I had my shop done, like you, I wanted a place to wash my car inside during nasty weather. I asked the concrete contractor if they could simply trowel an area about 20x20 to pitch down an inch or so into a drain. They tried and damned if it isn't just like the fire station, the low spot is a foot away from the drain!



Jeff-
__________________
You remind me of the timing on a turbo engine...
Reply With Quote
  #12  
Old 12-25-2012, 07:29 PM
onevoice onevoice is offline
Senior Member
 
Join Date: Oct 2006
Posts: 119
Thanks: 0
Thanked 0 Times in 0 Posts
Default

It is shocking how incompetent most construction workers are. In many years and many home renovation projects, I have yet to meet a true craftsman. My garage almost had the same issue, but I knew from experience to be there when ANY major activity was being done. My garage is about the same size, and I caught the concrete guys laying out about 1/2 of a concrete block's height of slope towards the door. I didn't know the spanish word for "flat", and it took some convincing to make them understand what I wanted.

I would have been very upset also, and the problem is that tearing out the floor and redoing will eat up more than the entire profit your contractor has in the job. He will do everything he can to avoid a re-pour.

The garage attached to my house was here when I moved in, and has so much slope a car will roll out if given a nudge. It is actually dangerous because the driveway is sloped away from the house, and the yard also. If a car rolled out it would end up 100ft away in a fence.
Reply With Quote
  #13  
Old 12-25-2012, 07:35 PM
Vegas69's Avatar
Vegas69 Vegas69 is offline
Senior Member
 
Join Date: Dec 2006
Posts: 8,692
Thanks: 87
Thanked 214 Times in 120 Posts
Default

With pretty much anything in life, if you fail to manage, it doesn't get done or turn out quite right. If it was in the contract or you called to remind him, I'd say it's his bad. If you were to busy, it falls on your lap.
__________________
Todd
Reply With Quote
  #14  
Old 12-25-2012, 07:59 PM
wiedemab's Avatar
wiedemab wiedemab is offline
Senior Member
 
Join Date: Oct 2005
Location: Batesville, IN
Posts: 1,473
Thanks: 0
Thanked 1 Time in 1 Post
Default

Quote:
Originally Posted by Vegas69 View Post
With pretty much anything in life, if you fail to manage, it doesn't get done or turn out quite right. If it was in the contract or you called to remind him, I'd say it's his bad. If you were to busy, it falls on your lap.
I know. ........
__________________
__________________
Brandon Wiedeman
'72 Suburban
'67 Chevy II -
https://lateral-g.net/forums/showthread.php4?t=46846

I have about 3 lifetimes worth of projects planned out in my head!
Reply With Quote
  #15  
Old 12-25-2012, 08:03 PM
Bad Bowtie Bad Bowtie is offline
Senior Member
 
Join Date: Apr 2006
Location: Central Florida
Posts: 230
Thanks: 4
Thanked 37 Times in 28 Posts
Default

Hey Brandon,
Just thought i'd share... I had a similiar issue when they poured my floor, I wasn't able to be home to oversee the work being done and ended up with a very level floor but the crew forgot to put a 1/2 drop at all 3 roll up door openings, so the concrete is flat all the way to the edge so now when the doors are shut and the rain blows against the door the water runs under the garage door bottom seal and lets water in (thankful it doesn't let much in). Just something i learned to live with but still dissapointing.
BB
Reply With Quote
  #16  
Old 12-25-2012, 08:03 PM
wiedemab's Avatar
wiedemab wiedemab is offline
Senior Member
 
Join Date: Oct 2005
Location: Batesville, IN
Posts: 1,473
Thanks: 0
Thanked 1 Time in 1 Post
Default

Quote:
Originally Posted by onevoice View Post
It is shocking how incompetent most construction workers are. In many years and many home renovation projects, I have yet to meet a true craftsman. My garage almost had the same issue, but I knew from experience to be there when ANY major activity was being done. My garage is about the same size, and I caught the concrete guys laying out about 1/2 of a concrete block's height of slope towards the door. I didn't know the spanish word for "flat", and it took some convincing to make them understand what I wanted.

I would have been very upset also, and the problem is that tearing out the floor and redoing will eat up more than the entire profit your contractor has in the job. He will do everything he can to avoid a re-pour.

The garage attached to my house was here when I moved in, and has so much slope a car will roll out if given a nudge. It is actually dangerous because the driveway is sloped away from the house, and the yard also. If a car rolled out it would end up 100ft away in a fence.
The work quality is fantastic. They are local guys and have been great to deal with. I will probably have no choice but to live with it. My budget probably won't allow a redo.
__________________
__________________
Brandon Wiedeman
'72 Suburban
'67 Chevy II -
https://lateral-g.net/forums/showthread.php4?t=46846

I have about 3 lifetimes worth of projects planned out in my head!
Reply With Quote
  #17  
Old 12-25-2012, 08:04 PM
wiedemab's Avatar
wiedemab wiedemab is offline
Senior Member
 
Join Date: Oct 2005
Location: Batesville, IN
Posts: 1,473
Thanks: 0
Thanked 1 Time in 1 Post
Default

Quote:
Originally Posted by Bad Bowtie View Post
Hey Brandon,
Just thought i'd share... I had a similiar issue when they poured my floor, I wasn't able to be home to oversee the work being done and ended up with a very level floor but the crew forgot to put a 1/2 drop at all 3 roll up door openings, so the concrete is flat all the way to the edge so now when the doors are shut and the rain blows against the door the water runs under the garage door bottom seal and lets water in (thankful it doesn't let much in). Just something i learned to live with but still dissapointing.
BB
I got the door openings done that way!
__________________
__________________
Brandon Wiedeman
'72 Suburban
'67 Chevy II -
https://lateral-g.net/forums/showthread.php4?t=46846

I have about 3 lifetimes worth of projects planned out in my head!
Reply With Quote
  #18  
Old 12-25-2012, 09:47 PM
wiedemab's Avatar
wiedemab wiedemab is offline
Senior Member
 
Join Date: Oct 2005
Location: Batesville, IN
Posts: 1,473
Thanks: 0
Thanked 1 Time in 1 Post
Default

Quote:
Originally Posted by ratman67 View Post
flat = plano level = nivel
Thanks for future reference...... These guys are local boys, and based on the last names....I'm guessing of German Catholic descent, like most around our area.

I was hoping that at least one person would chime in and say -- " my shop has a sloped floor and it really hasn't been a big issue". I guess most car people think like I do and want a level floor. Unfortunately for me, I wasn't there when they poured it to check to make sure it was done that way, which it appears may bite me in the ass.

I'm going to go to Dad's shop and check his floor. He has drains in the center of the building. I know his floor isn't level, but I'm not sure how much fall there is. It's harder to see when it slopes to the middle. If his is even close to what mine is, I'm probably going to just go with it. In the years that we've worked in his shop, I've never bitched about the floor slope........sooooo.

The other thing is, that even if his has the 1/8 per foot over 1/2 the building (sloping to the middle) it will be 1/2 the overall elevation change that I'm seeing since it slopes the entire 30 feet in mine.

I have a feeling this is going to be one of those frustrating and/or expensive life lessons. I know better too, is the part that makes me mad.
__________________
__________________
Brandon Wiedeman
'72 Suburban
'67 Chevy II -
https://lateral-g.net/forums/showthread.php4?t=46846

I have about 3 lifetimes worth of projects planned out in my head!
Reply With Quote
  #19  
Old 12-26-2012, 12:39 AM
glassman's Avatar
glassman glassman is offline
Lateral-g Supporting Member
 
Join Date: Apr 2012
Location: Livermore
Posts: 2,466
Thanks: 111
Thanked 84 Times in 62 Posts
Default

It's technically the difference between a shop and a garage, one with slope one without. I've worked on the1/8 per ft for years, don't even notice it. Shim the lift with ONLY steel shims, you probably already know that. IMO, the number one problem in the construction world is communication (how many of us grew up wanting to build/service).
Reply With Quote
  #20  
Old 12-26-2012, 01:05 AM
Track Junky's Avatar
Track Junky Track Junky is offline
Senior Member
 
Join Date: Apr 2010
Posts: 3,469
Thanks: 2
Thanked 12 Times in 7 Posts
Default

It's the norm for a contractor to slope a garage floor towards the garage door so that when it is being washed out the water heads in the correct direction. If he wasn't told before hand to make it flat he was just following typical building procedures.
__________________
Gaetano Cosentino
Reply With Quote
Reply


Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off

Forum Jump


All times are GMT -5. The time now is 09:23 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Copyright Lateral-g.net